New Jersey Solar Installation Update
The installed solar capacity reporting is broken down into two sections below. The Preliminary Update section provides program to date values as of the date listed below. There is no report accompanying the preliminary update. The End of Month Update section provides values based upon the most recently prepared end of month report, which contains detailed tables and a listing of all installed solar projects.
Preliminary Update
| NJCEP Solar Installed Projects Plus Pipeline Projects as of 5/24/13 | ||||
| Installed Solar Projects | ||||
| Interconnection Type |
Project Qty |
Installed Capacity (kW DC) |
% of Capacity |
Avg System Size (kW DC) |
| Behind the meter | 21.797 | 870,034.8 | 81.2% | 39.9 |
| Direct Grid Supply | 96 | 202,039.2 | 18.8% | 2,104.6 |
| Installed Totals | 21,893 | 1,072,074.1 | 100% | 49.0 |
| Solar Project Pipeline | ||||
| Interconnection Type |
Project Qty |
Total Capacity (kW DC) |
% of Capacity |
Avg System Size (kW DC) |
| Behind the meter | 4,590 | 186,911.1 | 27.4% | 40.7 |
| Direct Grid Supply | 49 | 495,003.8 | 72.6% | 10,102.1 |
| Pipeline Totals | 4,639 | 681,914.9 | 100.0% | 147.0 |
| Totals for All Projects | 26,532 | 1,753,988.9 | NA | 66.1 |
End Of Month Update
New Jersey solar installations now provide approximately 1,078.4 MW of installed capacity through 22,014 projects that have participated in the CORE Rebate Program, the Renewable Energy Incentive Program (REIP), and the SREC Registration Program.
| New Jersey Solar Installations by Interconnection Type as of 5/31/13 |
||||
| Interconnection Type |
Project Qty |
Installed Capacity (kW DC) |
Total Rebate $ |
% of Installed Capacity |
| Behind the meter | 21,913 | 873,131.0 | $363,510,421 | 81.0% |
| Direct Grid Supply | 101 | 205,279.9 | $- | 19.0% |
| Total* | 22,014 | 1,078,410.9 | $365,510,421 | 100.0% |
*Total= Program to date totals for installed solar projects: preliminary results subject to true-up based upon inspection results. Projects are considered as "Installed" after the Final as built documents are received and accepted. Additional processing steps are required prior to issuance of the NJ Certification number. Upon completion of all NJCEP program requirements, the project is labeled as complete.
| NJCEP Solar Project Pipeline as of 5/31/13 |
|||
| Interconnection Type | Project Qty | Total Capacity (kW DC) |
% of Capacity |
| Behind the Meter |
4,560
|
182,054.9
|
26.9%
|
| Direct Grid Supply |
49
|
495,003.8
|
73.1%
|
| Totals |
4,609
|
677,058.7
|
100.0%
|
Note 1:The projects summarized above and contained in the project list tab are all NJCEP accepted solar projects that have not yet reached the "Installed Project" status. The accepted projects listed in this report are NOT included in the installed project report for the same period.
| New Jersey Solar Pipeline Plus Installed Projects as of 5/31/13 |
|||
| Description | # Projects | Total kW dc | Report |
| Pipeline Projects | 4,609 | 677,058.7 | Solar Projects Pipeline |
| Installed Projects | 22,014 | 1,078,410.9 | Solar Installation Summary |
| Total* | 26,623 | 1,755,469.7 | |
NJCEP Solar Installed Capacity Forecast - This graph shows the cumulative installed solar capacity and a projection of future installed capacity for the combined totals for the CORE, REIP, and SRP programs.