PROJECT DESIGN
Five 1.5 MW GE wind turbines standing 397 feet tall located on the premises of the ACUA Wastewater Treatment Plant in coastal Atlantic City, NJ.
PROJECT SCHEDULE
Ground Breaking- September 2005
Turbine Erection - October~December 2005
Commercial Operation - December 2005
PROJECT TEAM
Leading wind energy marketer and developer Community Energy, Inc. has partnered with the ACUA, Babcock and Brown and Central Hudson Energy Group, Inc. as Jersey-Atlantic Wind, LLC to develop, construct, and operate the Jersey-Atlantic Wind Farm.
|